NBN Rollout Update April 2016: HFC construction commences

NBN indicates that 75 areas will move to construction phase this month, including the first areas to start HFC construction.
The company responsible for building the National Broadband Network, nbn, has released its monthly rollout map update revealing the latest areas to go into construction.
We've crunched the numbers and found that a total of 75 new brownfields (built up areas) have entered into the build phase around Australia this month - including the first 11 HFC areas to go into construction. The NBN was also switched on in 26 rollout areas and 49 fixed-wireless towers to service outer metropolitan fringes since this time last month. You can read more about the different NBN technologies in our detailed guide.
Just like last month, both the Australian Capital Territory and Northern Territory miss out on new rollout areas.
To find out if you're in the rollout plan and to see when you can expect services to become available, search for your address on finder.com.au's NBN tracker and subscribe to get notified as soon as your address is active.
Brownfields (Fibre) Rollout Update
Now active in these areas
NBN switched on 3 fibre rollout areas in built-up areas (brownfields) around NSW last month.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
2BLK-12 | Lalor Park, Kings Park | Active | Build Commenced |
2MAI-07 | Metford | Active | Build Commenced |
2MYF-02 | Mayfield East, Mayfield West, Mayfield | Active | Build Commenced |
Brownfields (Multi-Technology Mix) Rollout Update
Build has now commenced in these areas
Construction work has commenced for an additional 14 brownfields regions in NSW. These areas will primarily use Fibre to the Node technology, with some limited use of Fibre to the Premises and Fibre to the Basement technologies.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
2ALB-02 | East Albury | Build Commenced | N/A (new in April 2016) |
2AVA-03 | Avalon, Bilgola | Build Commenced | N/A (new in April 2016) |
2BUP-01 | Buff Point, San Remo | Build Commenced | N/A (new in April 2016) |
2KEL-03 | Stanhope Gardens, The Ponds, Kellyville Ridge | Build Commenced | Build Preparation |
2NAA-02 | Lisarow, Ourimbah | Build Commenced | N/A (new in April 2016) |
2NLB-04 | Salamander Bay, Corlette | Build Commenced | Build Preparation |
2NLB-05 | Soldiers Point, Salamander Bay | Build Commenced | Build Preparation |
2NRN-03 | Harrington Park, Narellan Vale, Smeaton Grange | Build Commenced | N/A (new in April 2016) |
2NRN-05 | Elderslie, Narellan, Narellan Vale | Build Commenced | N/A (new in April 2016) |
2PKE-05 | Berkeley, Lake Heights | Build Commenced | N/A (new in April 2016) |
2PKE-07 | Unanderra, Farmborough Heights | Build Commenced | Build Preparation |
2SHH-04 | Flinders, Blackbutt | Build Commenced | Build Preparation |
2WAG-04 | Kooringal, Mount Austin, Turvey Park | Build Commenced | N/A (new in April 2016) |
2WAG-10 | Glenfield Park, Tolland | Build Commenced | N/A (new in April 2016) |
Now active in these areas
NBN switched on 1 multi-technology rollout areas in built-up areas (brownfields) around NSW last month. These areas will primarily use Fibre to the Node technology, with some limited use of Fibre to the Premises and Fibre to the Basement technologies.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
2TGL-02 | Terrigal, Wamberal, North Avoca | Active | Build Commenced |
Fixed Wireless Rollout Update
Build has now commenced in these areas
Construction work has commenced for an additional 8 fixed wireless towers to service outer metropolitan fringes in NSW.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
2KMS-51-15-KEMS | Kempsey | Build Commenced | N/A (new in April 2016) |
2MAI-51-01-GRES | Gresford South | Build Commenced | N/A (new in April 2016) |
2MAI-51-04-DUCR | Duns Creek | Build Commenced | N/A (new in April 2016) |
2SIN-51-03-ELDE | Elderslie | Build Commenced | N/A (new in April 2016) |
2SIN-51-07-ROTH | Rothbury | Build Commenced | N/A (new in April 2016) |
2SIN-51-11-WINE | Winders Hill | Build Commenced | N/A (new in April 2016) |
2TUM-51-02-TUMU | Tumut | Build Commenced | N/A (new in April 2016) |
2TUM-51-03-GDGD | Gundagai | Build Commenced | N/A (new in April 2016) |
Now active in these areas
NBN switched on 12 fixed wireless rollout areas last month to service outer metropolitan fringes in NSW.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
2BMG-51-03-COBA | Cobargo | Active | Build Commenced |
2BMG-51-04-COOG | Coolagolite | Active | Build Commenced |
2BOM-51-01-BOMB | Bombala | Active | Build Commenced |
2BTH-51-04-EGLI | Eglinton | Active | Build Commenced |
2COM-51-02-DAIR | Dairymans | Active | Build Commenced |
2COM-51-03-GYGE | Gygederick Hill | Active | Build Commenced |
2COM-51-04-MTGL | Mt Gladstone | Active | Build Commenced |
2COM-51-06-NIMM | Nimmitabel | Active | Build Commenced |
2COM-51-08-BUNN | Bunyan | Active | Build Commenced |
2FNL-51-01-OAKL | Oaklands | Active | Build Commenced |
2FNL-51-04-JERI | Jerilderie | Active | Build Commenced |
2WGL-51-03-BARC | Barcoongere | Active | Build Commenced |
Brownfields (Fibre) Rollout Update
Now active in these areas
NBN switched on 2 fibre rollout areas in built-up areas (brownfields) around VIC last month.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
3BRA-10 | Mount Helen, Buninyong | Active | Build Commenced |
3KAL-07 | Langwarrin, Cranbourne South | Active | Build Commenced |
Brownfields (Multi-Technology Mix) Rollout Update
Build has now commenced in these areas
Construction work has commenced for an additional 16 brownfields regions in VIC. These areas will primarily use Fibre to the Node technology, with some limited use of Fibre to the Premises and Fibre to the Basement technologies.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
3COL-01 | Colac | Build Commenced | N/A (new in April 2016) |
3KGP-10 | Burnside Heights, Taylors Hill | Build Commenced | N/A (new in April 2016) |
3KIL-01 | Kilmore | Build Commenced | N/A (new in April 2016) |
3LOR-20 | Lorne | Build Commenced | N/A (new in April 2016) |
3MOR-02 | Mornington | Build Commenced | Build Preparation |
3MOR-05 | Mornington | Build Commenced | Build Preparation |
3OCG-06 | Point Lonsdale, Queenscliff | Build Commenced | N/A (new in April 2016) |
3RMS-01 | Lancefield, Romsey | Build Commenced | N/A (new in April 2016) |
3SUN-01 | Sunbury | Build Commenced | N/A (new in April 2016) |
3SUN-04 | Sunbury | Build Commenced | N/A (new in April 2016) |
3TAG-03 | Traralgon, Traralgon East | Build Commenced | N/A (new in April 2016) |
3TAG-04 | Traralgon | Build Commenced | N/A (new in April 2016) |
3WBO-01 | Warrnambool | Build Commenced | N/A (new in April 2016) |
3WBO-02 | Warrnambool | Build Commenced | N/A (new in April 2016) |
3WDG-02 | Bandiana, Baranduda, Wodonga | Build Commenced | N/A (new in April 2016) |
3WDG-05 | Wodonga | Build Commenced | N/A (new in April 2016) |
Fixed Wireless Rollout Update
Build has now commenced in these areas
Construction work has commenced for an additional 9 fixed wireless towers to service outer metropolitan fringes in VIC.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
3BAI-51-12-NICO | Nicholson East | Build Commenced | N/A (new in April 2016) |
3BAI-51-13-NUNU | Nungurner | Build Commenced | N/A (new in April 2016) |
3BAI-51-19-LAKU | Lake Bunga | Build Commenced | N/A (new in April 2016) |
3COL-51-03-BEEA | Beeac | Build Commenced | N/A (new in April 2016) |
3EAH-51-01-BRID | Bridgewater on Loddon | Build Commenced | N/A (new in April 2016) |
3EAH-51-04-MARO | Marong | Build Commenced | N/A (new in April 2016) |
3EAH-51-05-RAYW | Raywood | Build Commenced | N/A (new in April 2016) |
3REF-51-02-CARO | Cardross | Build Commenced | N/A (new in April 2016) |
3WAN-51-04-ELDO | Eldorado | Build Commenced | N/A (new in April 2016) |
Now active in these areas
NBN switched on 15 fixed wireless rollout areas last month to service outer metropolitan fringes in VIC.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
3ECH-51-01-BAMA | Bamawm Extension | Active | Build Commenced |
3ECH-51-02-ECHU | Echuca South | Active | Build Commenced |
3ECH-51-03-ECHC | Echuca Village | Active | Build Commenced |
3ECH-51-04-STRL | Strathallan North | Active | Build Commenced |
3ECH-51-05-WHAR | Wharparilla | Active | Build Commenced |
3ECH-51-06-WHAP | Wharparilla North | Active | Build Commenced |
3HMO-51-12-PENS | Penshurst | Active | Build Commenced |
3KER-51-02-KERA | Kerang | Active | Build Commenced |
3KER-51-04-KORO | Koroop | Active | Build Commenced |
3MFL-51-04-HQIT | Howqua Inlet | Active | Build Commenced |
3NMK-51-01-INVG | Invergordon | Active | Build Commenced |
3NMK-51-02-KATM | Katamatite | Active | Build Commenced |
3NMK-51-06-WUNG | Wunghnu | Active | Build Commenced |
3ORB-51-13-MEAS | Marlo East | Active | Build Commenced |
3SAL-51-15-COOU | Coongulla | Active | Build Commenced |
Brownfields (Fibre) Rollout Update
Now active in these areas
NBN switched on 3 fibre rollout areas in built-up areas (brownfields) around QLD last month.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
4GDN-02 | Goodna, Bellbird Park | Active | Build Commenced |
4MKY-07 | Racecourse, West Mackay, Ooralea | Active | Build Commenced |
4TNS-01 | Townsville City | Active | Build Commenced |
Brownfields (Multi-Technology Mix) Rollout Update
Build has now commenced in these areas
Construction work has commenced for an additional 19 brownfields regions in QLD. These areas will primarily use Fibre to the Node technology (or using HFC where indicated), with some limited use of Fibre to the Premises and Fibre to the Basement technologies.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
4BDS-01 | Beaudesert | Build Commenced | N/A (new in April 2016) |
4BUD-05 | Palmwoods | Build Commenced | N/A (new in April 2016) |
4FRV-02 | Frenchville, Norman Gardens | Build Commenced | N/A (new in April 2016) |
4HYP-01 | Hay Point | Build Commenced | N/A (new in April 2016) |
4IGH-01 | Ingham | Build Commenced | N/A (new in April 2016) |
4MYD-03 | Maroochydore | Build Commenced | N/A (new in April 2016) |
4NEW-02 | Rockville, Wilsonton, Wilsonton Heights | Build Commenced | N/A (new in April 2016) |
4NEW-06 | Cotswold Hills, Gowrie Junction, Torrington, Wilsonton | Build Commenced | N/A (new in April 2016) |
4RDC-65 (HFC) | Clontarf | Build Commenced | N/A (new in April 2016) |
4RDC-66 (HFC) | Clontarf, Kippa-Ring | Build Commenced | N/A (new in April 2016) |
4RDC-67 (HFC) | Margate | Build Commenced | N/A (new in April 2016) |
4RDC-68 (HFC) | Clontarf, Kippa-Ring, Margate | Build Commenced | N/A (new in April 2016) |
4RDC-69 (HFC) | Redcliffe | Build Commenced | N/A (new in April 2016) |
4RDC-71 (HFC) | Margate, Woody Point | Build Commenced | N/A (new in April 2016) |
4RDC-72 (HFC) | Kippa-Ring, Redcliffe | Build Commenced | N/A (new in April 2016) |
4RDC-73 (HFC) | Scarborough | Build Commenced | N/A (new in April 2016) |
4SAR-01 | Sarina | Build Commenced | N/A (new in April 2016) |
4SFT-01 | Seaforth | Build Commenced | N/A (new in April 2016) |
4SHF-02 | Trinity Beach | Build Commenced | Build Preparation |
Now active in these areas
NBN switched on 14 multi-technology rollout areas in built-up areas (brownfields) around QLD last month. These areas will primarily use Fibre to the Node technology, with some limited use of Fibre to the Premises and Fibre to the Basement technologies.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
4BRI-01 | Woorim, Bongaree | Active | Build Commenced |
4BRI-02 | Bongaree | Active | Build Commenced |
4BRI-03 | Bellara, Banksia Beach | Active | Build Commenced |
4BRI-04 | Welsby, White Patch, Banksia Beach | Active | Build Commenced |
4GYM-01 | Gympie | Active | Build Commenced |
4GYM-02 | Southside, Jones Hill | Active | Build Commenced |
4GYM-03 | Monkland, Gympie | Active | Build Commenced |
4GYM-04 | Gympie, Victory Heights, Araluen | Active | Build Commenced |
4NIN-01 | Ningi, Sandstone Point, Godwin Beach | Active | Build Commenced |
4WRN-01 | Brendale | Active | Build Commenced |
4WRN-04 | Lawnton | Active | Build Commenced |
4WRN-05 | Joyner, Lawnton, Warner, Bray Park | Active | Build Commenced |
4WRN-06 | Joyner, Warner, Cashmere | Active | Build Commenced |
4WRN-07 | Warner, Brendale | Active | Build Commenced |
Fixed Wireless Rollout Update
Build has now commenced in these areas
Construction work has commenced for an additional 15 fixed wireless towers to service outer metropolitan fringes in QLD.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
4AGW-51-01-AGNE | Agnes Water South | Build Commenced | N/A (new in April 2016) |
4AGW-51-02-AGNS | Agnes Water West | Build Commenced | N/A (new in April 2016) |
4BBE-51-23-KENG | Kensington | Build Commenced | N/A (new in April 2016) |
4BLB-51-05-TARM | Taromeo South | Build Commenced | N/A (new in April 2016) |
4CLP-51-01-ELIA | Elizabeth Peak | Build Commenced | N/A (new in April 2016) |
4GYM-51-05-CHAT | Chatsworth East | Build Commenced | N/A (new in April 2016) |
4KLC-51-01-KILO | Kilcoy | Build Commenced | N/A (new in April 2016) |
4KRO-51-11-BELE | Bell | Build Commenced | N/A (new in April 2016) |
4MAL-51-12-WITA | Witta North | Build Commenced | N/A (new in April 2016) |
4MLS-51-05-GUAN | Guanaba | Build Commenced | N/A (new in April 2016) |
4MRN-51-12-MIRA | Mirani | Build Commenced | N/A (new in April 2016) |
4NAN-51-07-TARO | Tarong North | Build Commenced | N/A (new in April 2016) |
4NBR-51-06-NAMW | Nambour West | Build Commenced | N/A (new in April 2016) |
4PPN-51-09-PRPS | Proserpine | Build Commenced | N/A (new in April 2016) |
4SAR-51-14-STLW | St Lawrence | Build Commenced | N/A (new in April 2016) |
Now active in these areas
NBN switched on 18 fixed wireless rollout areas last month to service outer metropolitan fringes in QLD.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
4ATH-51-07-MALA | Malanda | Active | Build Commenced |
4BIL-51-06-TEOO | Theodore | Active | Build Commenced |
4BLB-51-03-MOOE | Moore | Active | Build Commenced |
4GYM-51-01-AMAM | Amamoor | Active | Build Commenced |
4GYM-51-18-THPM | The Palms | Active | Build Commenced |
4GYM-51-30-IMBI | Imbil | Active | Build Commenced |
4GYM-51-31-KAND | Kandanga | Active | Build Commenced |
4HWR-51-03-BUXV | Buxtonville | Active | Build Commenced |
4INN-51-14-EARA | El Arish | Active | Build Commenced |
4INN-51-15-KBSR | Kurrimine Beach South | Active | Build Commenced |
4INN-51-17-MMTN | Mount Myrtle | Active | Build Commenced |
4INN-51-18-SILK | Silkwood | Active | Build Commenced |
4LAM-51-12-TANB | Tanby | Active | Build Commenced |
4MBO-51-06-MUNG | Mungar | Active | Build Commenced |
4MLS-51-05-GUAN | Guanaba | Active | Build Commenced |
4MUR-51-08-KKVK | Kilkivan | Active | Build Commenced |
4RHO-51-02-MILS | Millstream | Active | Build Commenced |
4RHO-51-03-MOUG | Mount Garnett | Active | Build Commenced |
Brownfields (Multi-Technology Mix) Rollout Update
Build has now commenced in these areas
Construction work has commenced for an additional 9 brownfields regions in SA. These areas will primarily use Fibre to the Node technology (or using HFC where indicated), with some limited use of Fibre to the Premises and Fibre to the Basement technologies.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
5GPC-06 | Ingle Farm, Pooraka, Walkley Heights | Build Commenced | N/A (new in April 2016) |
5GPC-07 | Mawson Lakes | Build Commenced | N/A (new in April 2016) |
5GUG-61 (HFC) | Cumberland Park, Daw Park | Build Commenced | N/A (new in April 2016) |
5JAM-01 | Jamestown | Build Commenced | N/A (new in April 2016) |
5KET-01 | Keith | Build Commenced | N/A (new in April 2016) |
5KGS-01 | Kingston SE, Pinks Beach | Build Commenced | N/A (new in April 2016) |
5MGI-01 | Meningie | Build Commenced | N/A (new in April 2016) |
5REL-07 | Reynella East, Woodcroft, Happy Valley | Build Commenced | Build Preparation |
5STI-01 | Aldgate, Crafers, Heathfield, Stirling | Build Commenced | N/A (new in April 2016) |
Fixed Wireless Rollout Update
Build has now commenced in these areas
Construction work has commenced for an additional 5 fixed wireless towers to service outer metropolitan fringes in SA.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
5NUR-51-03-GREE | Greenock | Build Commenced | N/A (new in April 2016) |
5PTL-51-09-WINH | Winter Hill | Build Commenced | N/A (new in April 2016) |
5YOW-51-01-COOB | Coobowie | Build Commenced | N/A (new in April 2016) |
5YOW-51-09-YORK | Yorketown | Build Commenced | N/A (new in April 2016) |
5YOW-51-14-CURM | Curramulka | Build Commenced | N/A (new in April 2016) |
Now active in these areas
NBN switched on 2 fixed wireless rollout areas last month to service outer metropolitan fringes in SA.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
5PTL-51-01-COFI | Coffin Bay | Active | Build Commenced |
5PTL-51-07-WANA | Wangary | Active | Build Commenced |
Brownfields (Fibre) Rollout Update
Now active in these areas
NBN switched on 2 fibre rollout areas in built-up areas (brownfields) around WA last month.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
6MDR-07 | Dudley Park, Coodanup | Active | Build Commenced |
6SPT-08 | Manning, Salter Point, Waterford, Karawara | Active | Build Commenced |
Brownfields (Multi-Technology Mix) Rollout Update
Build has now commenced in these areas
Construction work has commenced for an additional 13 brownfields regions in WA. These areas will primarily use Fibre to the Node technology (or using HFC where indicated), with some limited use of Fibre to the Premises and Fibre to the Basement technologies.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
6ARM-02 | Byford | Build Commenced | N/A (new in April 2016) |
6ARM-12 | Harrisdale, Piara Waters | Build Commenced | N/A (new in April 2016) |
6BNB-03 | East Bunbury, Carey Park | Build Commenced | Build Preparation |
6BUS-02 | Busselton, Geographe | Build Commenced | N/A (new in April 2016) |
6BUS-03 | Busselton, West Busselton | Build Commenced | N/A (new in April 2016) |
6COI-02 | Allanson, Collie | Build Commenced | N/A (new in April 2016) |
6JDL-60 (HFC) | Connolly,Ocean Reef | Build Commenced | N/A (new in April 2016) |
6JDL-62 (HFC) | Connolly, Ocean Reef | Build Commenced | N/A (new in April 2016) |
6QIN-02 | Jindalee, Quinns Rocks | Build Commenced | N/A (new in April 2016) |
6RKH-02 | East Rockingham, Rockingham | Build Commenced | N/A (new in April 2016) |
6RKH-03 | Cooloongup, Hillman, Rockingham | Build Commenced | N/A (new in April 2016) |
6RKH-06 | Safety Bay, Waikiki | Build Commenced | N/A (new in April 2016) |
6RKH-08 | Rockingham | Build Commenced | N/A (new in April 2016) |
Fixed Wireless Rollout Update
Build has now commenced in these areas
Construction work has commenced for an additional 8 fixed wireless towers to service outer metropolitan fringes in WA.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
6BRJ-51-02-BRUN | Brunswick | Build Commenced | N/A (new in April 2016) |
6PNJ-51-02-SOUT | South Yunderup | Build Commenced | N/A (new in April 2016) |
6PNJ-51-03-PINJ | Pinjarra | Build Commenced | N/A (new in April 2016) |
6PNJ-51-07-BARP | Barragup | Build Commenced | N/A (new in April 2016) |
6PRE-51-03-MOUN | Mount John | Build Commenced | N/A (new in April 2016) |
6TOO-51-02-CODL | Coondle | Build Commenced | N/A (new in April 2016) |
6TOO-51-05-TODS | Toodyay South | Build Commenced | N/A (new in April 2016) |
6TOO-51-07-GNGN | Gingin | Build Commenced | N/A (new in April 2016) |
Brownfields (Fibre) Rollout Update
Now active in these areas
NBN switched on 1 fibre rollout areas in built-up areas (brownfields) around TAS last month.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
7SHL-05 | St Leonards | Active | Build Commenced |
Brownfields (Multi-Technology Mix) Rollout Update
Build has now commenced in these areas
Construction work has commenced for an additional 4 brownfields regions in TAS. These areas will primarily use Fibre to the Node technology, with some limited use of Fibre to the Premises and Fibre to the Basement technologies.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
7DER-03 | Miandetta, Quoiba, Spreyton, Stony Rise, Tugrah, Aberdeen | Build Commenced | Build Preparation |
7HOB-12 | South Hobart, Wellington Park, Fern Tree | Build Commenced | Build Preparation |
7HUL-01 | Franklin, Huonville, Ranelagh | Build Commenced | N/A (new in April 2016) |
7NWT-02 | Berriedale, Chigwell, Claremont | Build Commenced | N/A (new in April 2016) |
Fixed Wireless Rollout Update
Build has now commenced in these areas
Construction work has commenced for an additional 7 fixed wireless towers to service outer metropolitan fringes in TAS.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
7CLT-51-11-OATL | Oatlands | Build Commenced | N/A (new in April 2016) |
7CLT-51-12-PART | Parattah | Build Commenced | N/A (new in April 2016) |
7CYE-51-08-GEEV | Geeveston | Build Commenced | N/A (new in April 2016) |
7CYE-51-12-LUNE | Lune River | Build Commenced | N/A (new in April 2016) |
7DSF-51-10-MURD | Murdunna East | Build Commenced | N/A (new in April 2016) |
7HUL-51-12-CHIM | Chimney Pot | Build Commenced | N/A (new in April 2016) |
7RAO-51-08-ERRI | Erriba | Build Commenced | N/A (new in April 2016) |
Now active in these areas
NBN switched on 2 fixed wireless rollout areas last month to service outer metropolitan fringes in TAS.
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
7NOL-51-12-MOUR | Mount Rivulet | Active | Build Commenced |
7SWA-51-02-CBEE | Coles Bay East | Active | Build Commenced |
New Developments (Fibre) Rollout Update
Build preparation has commenced in these new developments
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
AYCA-18U14O | Jaques Apartments (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-1D309I | Moncrieff Residential Estate (Stage 3 (West)) | Build Preparation | N/A (new in April 2016) |
AYCA-1GXOQF | Hepburn (Magnolia) Apartments (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1H13L5 | Elements Estate (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-1HOLRT | Ballina Heights (Stage 8a) | Build Preparation | N/A (new in April 2016) |
AYCA-1IDA1V | RIX RD (Stage 6) | Build Preparation | N/A (new in April 2016) |
AYCA-1II50T | Mason Point (Stage 2A) | Build Preparation | N/A (new in April 2016) |
AYCA-1IMEN1 | 20 Bush Boulevard (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-1J1R9S | Northlakes Estate (Stage 45) | Build Preparation | N/A (new in April 2016) |
AYCA-1JKNHH | Lot 112 Schofields Rd Schofields (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1JUBGD | EVE (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1KKXKB | Lucent (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1L4KCF | Wentworth Point Marinas Block G (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-1LXBAR | Skyring Apartments (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1MIEQM | Moncrieff Residential Estate (Stage 2B (East)) | Build Preparation | N/A (new in April 2016) |
AYCA-1NDODB | Lampada (Stage 8) | Build Preparation | N/A (new in April 2016) |
AYCA-1NZK6Q | 61-67 Caboolture River Rd (Stage 4) | Build Preparation | N/A (new in April 2016) |
AYCA-1NZKFI | 61-67 Caboolture River Rd (Stage 5) | Build Preparation | N/A (new in April 2016) |
AYCA-1O2U12 | 1 - 5 Weston Street, Rosehill (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1O3I19 | Pentridge Coburg (Stage Pentridge 7 - West - 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1O7TFT | Riverstone Crossing (Stage 13A) | Build Preparation | N/A (new in April 2016) |
AYCA-1O8ZKV | Marsden Heights (Stage 6) | Build Preparation | N/A (new in April 2016) |
AYCA-1P5C2I | Katandra Rise Estate (Stage 5) | Build Preparation | N/A (new in April 2016) |
AYCA-1QFWWC | 29&31 Hezlett Road (Stage 1, 2, 3, 4) | Build Preparation | N/A (new in April 2016) |
AYCA-1QG17L | 33&35 Hezlett Road (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1QKQN7 | Spring Farm (Stage P305) | Build Preparation | N/A (new in April 2016) |
AYCA-1QVCZX | 209 Bay Street (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1RX8BR | ARENA (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-1S8W9Y | Adresse (Stage 5) | Build Preparation | N/A (new in April 2016) |
AYCA-1SC3UK | ARV - The Ponds (Stage 3&4) | Build Preparation | N/A (new in April 2016) |
AYCA-1SGVOG | Jinglers Creek Estate (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-1SXQ4Z | Lot 10,50 & 700 Ocean Reef Gnangara (Stage 4B Phase 2) | Build Preparation | N/A (new in April 2016) |
AYCA-1TQ2MG | Tower Rise Estate (Stage 4) | Build Preparation | N/A (new in April 2016) |
AYCA-1TXF6J | COASTAL PARK ESTATE (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-1U0N4F | Camberwarra Primary School Redevelopment (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1VD93W | Riverbank (Stage 3B) | Build Preparation | N/A (new in April 2016) |
AYCA-1W24PL | Rockbank North (Woodlea) (Stage 4) | Build Preparation | N/A (new in April 2016) |
AYCA-1WA1SS | Manor Lakes (Stage 132) | Build Preparation | N/A (new in April 2016) |
AYCA-1WAY3D | Allura Estate (Stage 40) | Build Preparation | N/A (new in April 2016) |
AYCA-1WB0YC | Allura Estate (Stage 41) | Build Preparation | N/A (new in April 2016) |
AYCA-1WCWAU | Ormeau Ridge (Stage 23) | Build Preparation | N/A (new in April 2016) |
AYCA-1WDK30 | Highland Reserve - L2097 Augustus Dr (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1WVIL6 | Broughton Street - Moss Vale (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-1X178Z | 565 Hume (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-1X4PVA | Jubilee (Precinct 1) (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1XA8LF | 26 Park Street, Riverstone (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1XD1CL | West Baldivis (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-1XIC4V | Timbertop 8-13 (Stage 10) | Build Preparation | N/A (new in April 2016) |
AYCA-1XJK6S | 46 Ashbourne Road Community Development (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1XZNCT | Timbertop 8-13 (Stage 9) | Build Preparation | N/A (new in April 2016) |
AYCA-1Y0UYI | Warralily Coast (Stage 77) | Build Preparation | N/A (new in April 2016) |
AYCA-1YQTD5 | Elements Estate (Stage 4) | Build Preparation | N/A (new in April 2016) |
AYCA-1Z9RA4 | 2/28 Lawson - 2611 Developments Pty Ltd (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-1ZLNCY | Livingston Development (Stage 13) | Build Preparation | N/A (new in April 2016) |
AYCA-1ZNFWN | Oakmont (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-2010S4 | Rangeview Estate (Stage 8&9) | Build Preparation | N/A (new in April 2016) |
AYCA-201KPV | Elements Estate (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-202OSS | Mulgoa Rise (Stage 5) | Build Preparation | N/A (new in April 2016) |
AYCA-20FGQ3 | The Heartlands (Stage 15) | Build Preparation | N/A (new in April 2016) |
AYCA-20TBX3 | South Beach Farm Estate (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-216WYH | 80-84 Kildare Road, Blacktown (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-21ANQJ | alban gardens (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-21RDPV | Charlemont Rise (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-21U2MF | Tumbi Heights Estate (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-227I3Z | Livingston Development (Stage 12) | Build Preparation | N/A (new in April 2016) |
AYCA-22MJDX | Stockdale Fields Estate (v1) (Stage 6) | Build Preparation | N/A (new in April 2016) |
AYCA-22OKF4 | 50 Pine Road Richlands (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-22ON4N | 50 Pine Road Richlands (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-22YN6S | Lot 9007 Shallcross Street Yangebup (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-231YWS | Springridge Estate (Stage 4E) | Build Preparation | N/A (new in April 2016) |
AYCA-234FJ0 | Rockbank North (Woodlea) (Stage 5) | Build Preparation | N/A (new in April 2016) |
AYCA-237Q8T | 90 Harvest Home Road, Wollert (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-23E4GJ | Lot 45 Wright Road Piara Waters (Stage 2B) | Build Preparation | N/A (new in April 2016) |
AYCA-23E54B | HUB (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-23TSZU | Jubilee (Precinct 1) (Stage 5) | Build Preparation | N/A (new in April 2016) |
AYCA-245Z7T | Sovereign Hills (Stage Sterling Green 1a) | Build Preparation | N/A (new in April 2016) |
AYCA-24BI7H | Blackrock Development (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-24QE71 | Ward 20 (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-24UHVI | Woods Road Developments Pty Ltd (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-24WWS1 | The Village at Wellard (Stage VCS4) | Build Preparation | N/A (new in April 2016) |
AYCA-24XIMK | Quarters (Stage 11) | Build Preparation | N/A (new in April 2016) |
AYCA-24XZAL | Lot 9006 Shallcross Street, Yangebup (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-250EOR | Jubilee (Precinct 1) (Stage 6) | Build Preparation | N/A (new in April 2016) |
AYCA-250T5O | Lot 107 Barfield Road, Hammond Park (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-256LSL | Dwyer Street, Kalkallo (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-263C5A | 82-88 Schofields Rd (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-26A3CB | Lot 32 Sciano Avenue, Success (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-26I6MN | Mernda Villages (Stage 63) | Build Preparation | N/A (new in April 2016) |
AYCA-28XC74 | Sovereign Pocket (The Outlook) (Stage 5B) | Build Preparation | N/A (new in April 2016) |
AYCA-2975T1 | Flamingo Park Estate (Stage 3 and 4) | Build Preparation | N/A (new in April 2016) |
AYCA-2977MS | Citrine Road (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-29BQNX | Strzelecki Views Estate (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-29PCA6 | Dunsborough Lakes (Stage 1B) | Build Preparation | N/A (new in April 2016) |
AYCA-2BCOJN | Ashlar (Stage 42) | Build Preparation | N/A (new in April 2016) |
AYCA-2BE2VV | Daintree Estate (Stage 5.1) | Build Preparation | N/A (new in April 2016) |
AYCA-2BMUME | Dunsborough Lakes (Stage 18) | Build Preparation | N/A (new in April 2016) |
AYCA-2CKA87 | Brentford Pde Units (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2CP0DW | Rockbank North (Woodlea) (Stage 6) | Build Preparation | N/A (new in April 2016) |
AYCA-2CQX8A | TALLOWOOD (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2CX5IN | Adresse (Stage 7) | Build Preparation | N/A (new in April 2016) |
AYCA-2CZYOM | Sienna Wood (Stage Riverbend Stage 5 to 8) | Build Preparation | N/A (new in April 2016) |
AYCA-2D9LX9 | Lyndarum (Stage ID9) | Build Preparation | N/A (new in April 2016) |
AYCA-2DLMZN | Belle Eden Estate (Stage 2E & 2F) | Build Preparation | N/A (new in April 2016) |
AYCA-2DLWQO | Gardens Estate (Stage 4) | Build Preparation | N/A (new in April 2016) |
AYCA-2DT1AY | Pinnacle Apartments (Stage SP2) | Build Preparation | N/A (new in April 2016) |
AYCA-2EQI4S | 52 Banksia Grove (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2F34QG | Willowdale Retirement Village (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-2F5TT1 | Collier Units (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2FYTBZ | Shorehaven Alkimos (Stage 5) | Build Preparation | N/A (new in April 2016) |
AYCA-2G32NX | ALMA (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2GIG8S | KINSELLAS ROAD WEST (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2GRPSA | 2 Barney Street, Kiama (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2HC7EW | Yumi (Stage Franklin 1/127) | Build Preparation | N/A (new in April 2016) |
AYCA-2HERI7 | Kilora - 335 Grices Road (Stage 8) | Build Preparation | N/A (new in April 2016) |
AYCA-2HI7EC | 36 Paxford Drive, Cranbourne North, Vic (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2HJEGK | Akora Apartments (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2HKCY0 | Greentree townhouses (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2HP9XC | VW Sunshine Coast (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2HTGM3 | Jubilee (Precinct 1) (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-2HW00E | The Heights (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2I0D1M | The Heights (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-2I98LP | Kilora - 335 Grices Road (Stage 9) | Build Preparation | N/A (new in April 2016) |
AYCA-2IMGZ1 | 13 McMillan St, Victoria Park, WA (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2IQL0L | Timbertop (Stage Lot R) | Build Preparation | N/A (new in April 2016) |
AYCA-2IW0JF | Epping Warehouses (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2IYFPG | Garden Terrace (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2J5UH0 | Paradise Villas (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2JKJEY | Cavalry Rd, Sippy Downs (Stage 5) | Build Preparation | N/A (new in April 2016) |
AYCA-2JKRR6 | IRT Woodlands (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-2JLZIQ | HERAN BUILDING GROUP PTY LTD (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2JY9WW | Manima Developments Pty Ltd (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2K18Y3 | Horizons Village (Stage 7) | Build Preparation | N/A (new in April 2016) |
AYCA-2K71DS | Birtinya Estate (Stage DPA 4 Park) | Build Preparation | N/A (new in April 2016) |
AYCA-2K7I83 | Lot 20 Rockingham Road, Munster (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2KCUVF | BA - 204 Kooyong Rd Apartments (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2KYRJJ | Blue Skye (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2M9KDU | Tianna (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2MBZO2 | Springbrook & Bellmere (Stage 14 & 15) | Build Preparation | N/A (new in April 2016) |
AYCA-2MO8KO | Parkside Coomera (Stage 6) | Build Preparation | N/A (new in April 2016) |
AYCA-2MOSD8 | 64 Michael Avenue (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2MP6CC | Millsteam and Bluff Road (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2NDK6M | Jubilee Pocket (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-2NFKL0 | Miranda Apartments (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-2NGB1K | WattleViews Stage (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-2NOB45 | 188 Churchill Road (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2NYYW5 | Park Holme (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2OFR38 | Woolworths Spring Farm (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2OQF3N | ROSENDALE ESTATE (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2P0U3J | Manning Community Hub (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2P0U94 | The Rivergums (Stage 11A) | Build Preparation | N/A (new in April 2016) |
AYCA-2PBQFJ | 102 Kanahooka Rd (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2PIRBA | VEER (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2PLOH2 | Brittains Road (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-2PPNUK | Lot 22 Collier Drive South Hedland WA (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2PRIUF | Birtinya Estate (Stage Oceanside - Stage 12) | Build Preparation | N/A (new in April 2016) |
AYCA-2PRUPL | Birtinya Estate (Stage Oceanside - Stage 14) | Build Preparation | N/A (new in April 2016) |
AYCA-2PRUSQ | Birtinya Estate (Stage Oceanside - Stage 13) | Build Preparation | N/A (new in April 2016) |
AYCA-2PRW7Y | Birtinya Estate (Stage Oceanside - Stage 15) | Build Preparation | N/A (new in April 2016) |
AYCA-2PS09E | Birtinya Estate (Stage Oceanside - Stage 16) | Build Preparation | N/A (new in April 2016) |
AYCA-2PTXGU | Lot 379 Gawler Road (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2Q4OEG | 27 Clydesdale Road. Airport West (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2Q7VK9 | Quay Boulevard, Werribee South (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2QDKKR | Oakwood Rise (Stage 4) | Build Preparation | N/A (new in April 2016) |
AYCA-2QJJ7X | 25 Supreme Loop (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2RLNIW | Signature Apartments (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2RNK60 | The Heartlands (Stage 19b) | Build Preparation | N/A (new in April 2016) |
AYCA-2RNQCE | Alma Heights (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2S2PZX | Lamington (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2SVFA4 | Oak St (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2TFGF0 | GV Hospice (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2UEW80 | Martin Lynch (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2UT97J | 30 POLGLAZE (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2UVDTR | Macquarie St Project (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2V0RO2 | Wilson Street, West Mackay (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2VAC3U | 18 David St Nundah (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2VHXEN | IRT Woodlands (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-2VLKER | A Primus & D Primus & D Primus (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2VSHJ3 | Peninsula (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2VYKS2 | 48 & 50 Grey Street (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2W24JT | 4 Leicester Square, Tullamarine (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2W4QEY | 235 Alderley St (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2W5KAY | Bunnings Gungahlin (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2W8HMM | 48 Mariah Crescent, Oakdowns, Tas (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2XE5WL | 33 Pioneer St (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2Y348T | 276 Alderley Street (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2Y8YGH | Algona Road (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2YNJ60 | 18 Boronia Street (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2Z6OE7 | 18 Parer Road, Airport West (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-2ZGMLX | Adresse (Stage 6) | Build Preparation | N/A (new in April 2016) |
AYCA-2ZIWXP | Lot 9000 Baile Road Canning Vale (Stage 5) | Build Preparation | N/A (new in April 2016) |
AYCA-300JW3 | 23 Eumarella Street, Tullamarine (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-3091VT | Woodvale (Stage 2E) | Build Preparation | N/A (new in April 2016) |
AYCA-313TAO | The Lodge Estate (Stage 2) | Build Preparation | N/A (new in April 2016) |
AYCA-33NV6J | Paragon Estate (Stage Paragon 3B Lots 13 - 77) | Build Preparation | N/A (new in April 2016) |
AYCA-33O0H5 | Paragon Estate (Stage Paragon 3B Lots 50 - 56) | Build Preparation | N/A (new in April 2016) |
AYCA-E8WIP | Cronulla Sharks Redevelopment (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-EACM8 | Harbour Apartments (Stage 1) | Build Preparation | N/A (new in April 2016) |
AYCA-IJ05P | Glenhaven Park (Stage 3) | Build Preparation | N/A (new in April 2016) |
AYCA-ZA2LC | Adresse (Stage 2) | Build Preparation | N/A (new in April 2016) |
Build has now commenced in these new developments
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
AYCA-10J9NT | Riva (Stage 11 - GH) | Build Commenced | Build Preparation |
AYCA-10UTLQ | Westmark (Stage Tower 1) | Build Commenced | Build Preparation |
AYCA-12P7G3 | Warrs Road Project Pty Ltd (Stage 1) | Build Commenced | Build Preparation |
AYCA-13H1E2 | Harrison Reserve (Stage 2) | Build Commenced | Build Preparation |
AYCA-14RS2L | EDGELEA (Stage Precinct 2) | Build Commenced | Build Preparation |
AYCA-14VCN1 | 120 Alma Road (Stage 1B) | Build Commenced | Build Preparation |
AYCA-152DE1 | Marsden Park Precinct (Stage 10) | Build Commenced | Build Preparation |
AYCA-181904 | Skyring at Waterfront (Stage 1) | Build Commenced | Build Preparation |
AYCA-184WNN | Carre Residences Development (Stage 3) | Build Commenced | Build Preparation |
AYCA-18VEFH | The Outlook, Delroy Park (Stage 13a&b) | Build Commenced | Build Preparation |
AYCA-19AQUM | Vintage (Stage The Elms SG4) | Build Commenced | Build Preparation |
AYCA-19DZSK | Westmark (Stage Tower 2) | Build Commenced | Build Preparation |
AYCA-19XRUO | Muirhead (Stage 5B) | Build Commenced | Build Preparation |
AYCA-1A5OWY | Muirhead (Stage 5C) | Build Commenced | Build Preparation |
AYCA-1A5SFE | Muirhead (Stage 5D) | Build Commenced | Build Preparation |
AYCA-1A5SNZ | Muirhead (Stage 5E) | Build Commenced | Build Preparation |
AYCA-1AIL3H | Ballina Heights (Stage 8b-2) | Build Commenced | Build Preparation |
AYCA-1AVH72 | Sienna Wood (Stage Riverbend Stage 2) | Build Commenced | Build Preparation |
AYCA-1B20SQ | Bluewattle (Stage 6) | Build Commenced | Build Preparation |
AYCA-1B214P | Bluewattle (Stage 7) | Build Commenced | Build Preparation |
AYCA-1CDOM3 | Norfolk Estates Pty Ltd (Stage 6 & 6B) | Build Commenced | Build Preparation |
AYCA-1CPCS9 | Moncrieff Residential Estate (Stage 1A (East)) | Build Commenced | Build Preparation |
AYCA-1CRHQQ | 30 Hardys Road, Clyde North (Stage 3A) | Build Commenced | Build Preparation |
AYCA-1DFTFN | Red Castle (Stage 1) | Build Commenced | Build Preparation |
AYCA-1DFTWX | Bribie Lakes (Stage 1A) | Build Commenced | Build Preparation |
AYCA-1DJUKE | Harold Park (Stage 4B) | Build Commenced | Build Preparation |
AYCA-1DXK2M | Bribie Lakes (Stage 2) | Build Commenced | Build Preparation |
AYCA-1DXK4K | Bribie Lakes (Stage 4) | Build Commenced | Build Preparation |
AYCA-1FIP2E | The Outlook (Stage 6B) | Build Commenced | Build Preparation |
AYCA-1FKXCT | Imagine Strathfieldsaye East (Stage 5) | Build Commenced | Build Preparation |
AYCA-1HA8EL | Willowdale Retirement Village (Stage A) | Build Commenced | Build Preparation |
AYCA-1HRD5N | ELSTERNWICK PLACE (Stage 1) | Build Commenced | Build Preparation |
AYCA-1IARWL | The Range (Stage 4C) | Build Commenced | Build Preparation |
AYCA-1IN70Y | Newstead Central Stage 1 (Stage 1) | Build Commenced | Build Preparation |
AYCA-1IV3RW | Habitat - Riverpoint Stage 2A & 2B (Stage 1) | Build Commenced | Build Preparation |
AYCA-1IYXE2 | Huntlee Stage 1 (Stage Precinct 4) | Build Commenced | Build Preparation |
AYCA-1J1R0E | Northlakes Estate (Stage 48A) | Build Commenced | Build Preparation |
AYCA-1J1R4E | Northlakes Estate (Stage 48) | Build Commenced | Build Preparation |
AYCA-1J4V7I | Muirhead (Stage 6.1) | Build Commenced | Build Preparation |
AYCA-1J527U | Muirhead (Stage 6.2) | Build Commenced | Build Preparation |
AYCA-1JNEYK | Fairview Estate (Stage 8) | Build Commenced | Build Preparation |
AYCA-1JWECF | Bloom Estate (Stage 1) | Build Commenced | Build Preparation |
AYCA-1JYJHR | Central Village (Stage 3) | Build Commenced | Build Preparation |
AYCA-1K16IU | Lawson South (Stage 1A & 1B) | Build Commenced | Build Preparation |
AYCA-1LG4RD | OXFORD CROWN (Stage 1) | Build Commenced | Build Preparation |
AYCA-1LLEGM | 830 Bridge Inn Road (Stage 3B) | Build Commenced | Build Preparation |
AYCA-1M24EK | Waterhaven Estate (Stage 11) | Build Commenced | Build Preparation |
AYCA-1NBJUP | Northpoint (Stage 8B) | Build Commenced | Build Preparation |
AYCA-1NHUJ7 | Attamurra Heights (Stage 2C) | Build Commenced | Build Preparation |
AYCA-1O2TY4 | Ashley Court (Stage 1) | Build Commenced | Build Preparation |
AYCA-1O2UGV | Ashley Court (Stage 2) | Build Commenced | Build Preparation |
AYCA-1OC25Q | 72 Tuckey St, Mandurah (Stage 1) | Build Commenced | Build Preparation |
AYCA-1OPRTG | Taskers (Stage 3 - Townhouses) | Build Commenced | Build Preparation |
AYCA-1PGDME | Centrus (Stage 1-E1) | Build Commenced | N/A (new in April 2016) |
AYCA-1PTQQR | Station Road Residential Development (Stage 1) | Build Commenced | Build Preparation |
AYCA-1Q54K1 | The Woodstore (Stage 1) | Build Commenced | Build Preparation |
AYCA-1QGC39 | Carine Rise Development (Stage Lot 32 MDU) | Build Commenced | Build Preparation |
AYCA-1QM7LK | Hillview Rise (Stage 4 & 5) | Build Commenced | N/A (new in April 2016) |
AYCA-1QVPXB | White Box Rise (Stage 13) | Build Commenced | Build Preparation |
AYCA-1RHCPE | 127 Flynn Circuit (Stage B3) | Build Commenced | Build Preparation |
AYCA-1RMQXT | Wellard Glen (Stage 2) | Build Commenced | Build Preparation |
AYCA-1RQ55V | ERA Estate Capalaba (Stage 6) | Build Commenced | Build Preparation |
AYCA-1RTG3Y | Kilora - 335 Grices Road (Stage 5) | Build Commenced | Build Preparation |
AYCA-1S5RB0 | TATTON PARK (Stage 3A and 3B) | Build Commenced | Build Preparation |
AYCA-1SAC1M | Livingston (Stage 8) | Build Commenced | Build Preparation |
AYCA-1SB59O | Berrimah Business Park, Stage 2A (Stage 2A) | Build Commenced | Build Preparation |
AYCA-1T1X1R | Lucas (Stage C1) | Build Commenced | Build Preparation |
AYCA-1T2Q30 | Vivente (Stage 1) | Build Commenced | N/A (new in April 2016) |
AYCA-1TRLG8 | Alexander Road (Stage 1) | Build Commenced | Build Preparation |
AYCA-1TWYMH | Osprey Waters, Erskine (Stage 3) | Build Commenced | Build Preparation |
AYCA-1TXF0H | COASTAL PARK ESTATE (Stage 2) | Build Commenced | Build Preparation |
AYCA-1U8G8Z | Cheltenham Village (Stage 1) | Build Commenced | Build Preparation |
AYCA-1U8GAU | Canopy (Stage 3) | Build Commenced | Build Preparation |
AYCA-1UHEDO | Ascot Estate, Pakenham (Stage 4) | Build Commenced | Build Preparation |
AYCA-1UKMB4 | Lucas (Stage C2) | Build Commenced | Build Preparation |
AYCA-1URT7N | Insignia (Stage G1) | Build Commenced | Build Preparation |
AYCA-1UXOYP | Everton Gardens Estate (Stage 6A) | Build Commenced | Build Preparation |
AYCA-1UXQQP | Timbertop (Stage 6) | Build Commenced | Build Preparation |
AYCA-1V2FUE | Allura Estate (Stage 36) | Build Commenced | Build Preparation |
AYCA-1VCTTA | Lot 45 Wright Road Piara Waters (Stage 2A) | Build Commenced | Build Preparation |
AYCA-1VD9A9 | Riverbank (Stage 9C) | Build Commenced | Build Preparation |
AYCA-1VDBLO | Warner Lakes The Reserve (Stage 6) | Build Commenced | Build Preparation |
AYCA-1VDE4E | Warner Lakes The Reserve (Stage 7) | Build Commenced | Build Preparation |
AYCA-1VGIKG | The Fairways (Stage Y) | Build Commenced | Build Preparation |
AYCA-1VGQRO | Carine Rise - Momentum (Stage Lot 15) | Build Commenced | Build Preparation |
AYCA-1VIWQR | Port Coogee - Village Shopping Centre - Lot 796 (Stage 1) | Build Commenced | Build Preparation |
AYCA-1VK6PN | Mernda Villages (Stage 53) | Build Commenced | Build Preparation |
AYCA-1VK6UV | Mernda Villages (Stage 54) | Build Commenced | Build Preparation |
AYCA-1VRID8 | Mountview Estate (Stage 9D) | Build Commenced | Build Preparation |
AYCA-1W20P9 | Rockbank North (Woodlea) (Stage 3) | Build Commenced | Build Preparation |
AYCA-1W60Z8 | Augustine Heights Extension (Stage 17) | Build Commenced | Build Preparation |
AYCA-1W6121 | Augustine Heights Extension (Stage 18) | Build Commenced | Build Preparation |
AYCA-1W6XUR | Yanchep Golf Estate (Stage 6B) | Build Commenced | Build Preparation |
AYCA-1WA7PV | Bells Reach Estate (Stage 26) | Build Commenced | Build Preparation |
AYCA-1WEGAT | Habitat (Stage 2) | Build Commenced | Build Preparation |
AYCA-1WGR0N | Parklakes Estate (Stage Precinct R2 - 2) | Build Commenced | Build Preparation |
AYCA-1WKG5J | Lots 81 & 82 Cooper Street, Madeley (Stage 2) | Build Commenced | Build Preparation |
AYCA-1WXW87 | The Meadows (Stage 2 Karingal - 2B) | Build Commenced | Build Preparation |
AYCA-1WXWJI | The Meadows (Stage 3 Karingal) | Build Commenced | Build Preparation |
AYCA-1WYYIZ | ARV - The Ponds (Stage 2) | Build Commenced | Build Preparation |
AYCA-1X1JHI | Glenfield Beach Subdivision (Stage 1) | Build Commenced | Build Preparation |
AYCA-1X23QF | Lot 450 Lord Street Caversham (Stage 1) | Build Commenced | Build Preparation |
AYCA-1XEEO0 | The Village at Wellard (Stage 39) | Build Commenced | Build Preparation |
AYCA-1XJQXF | COSTOJIC (Stage 1A) | Build Commenced | Build Preparation |
AYCA-1XO0KO | Viewpoint, Huntly (Stage Precinct C5) | Build Commenced | Build Preparation |
AYCA-1XR4N1 | Baranduda Grove (Stage 1) | Build Commenced | Build Preparation |
AYCA-1Y4SKZ | Tullimbar Village (Stage 2B) | Build Commenced | Build Preparation |
AYCA-1Y81GC | Highgrove Estate (Stage 5) | Build Commenced | Build Preparation |
AYCA-1YN0DO | Virginia Grove (Stage 1) | Build Commenced | Build Preparation |
AYCA-1Z7IDN | Bellevue Estate (Stage 8) | Build Commenced | Build Preparation |
AYCA-1ZBFHU | Gateway of Findon (Stage 4) | Build Commenced | Build Preparation |
AYCA-1ZEMF3 | Grandvue Estate (Stage 10B) | Build Commenced | Build Preparation |
AYCA-207APO | Springlake Subdivision, Mt Barker (Stage 1B) | Build Commenced | Build Preparation |
AYCA-20BFSL | The Lindfield (Stage 1) | Build Commenced | Build Preparation |
AYCA-20LTWW | Treeby Park (Stage 1) | Build Commenced | Build Preparation |
AYCA-20RPIG | Lifestyles Bell Park Retirement Village (Stage 2) | Build Commenced | Build Preparation |
AYCA-212RX0 | The Ternary (Stage 1) | Build Commenced | Build Preparation |
AYCA-21BVJG | Brookford (Stage 2A) | Build Commenced | Build Preparation |
AYCA-21TTNZ | My Home & The River (new policy) (Stage 5) | Build Commenced | Build Preparation |
AYCA-21WZNA | Gateway Lifestyle Ballarat (Stage 1 & 2) | Build Commenced | Build Preparation |
AYCA-226O9X | East Leppington (Stage 8A) | Build Commenced | Build Preparation |
AYCA-226WUH | East Leppington (Stage 8B) | Build Commenced | Build Preparation |
AYCA-226WXS | East Leppington (Stage 8C) | Build Commenced | Build Preparation |
AYCA-22BFP9 | Merrifield Residential (Stage 15) | Build Commenced | Build Preparation |
AYCA-22CPCD | 73 Kintail Road Applecross (Stage 1) | Build Commenced | Build Preparation |
AYCA-22CPG7 | Lot 21 Cross Road Coogee (Stage 1) | Build Commenced | Build Preparation |
AYCA-22DZMR | 293 Foxwell Rd Coomera (Stage 4) | Build Commenced | Build Preparation |
AYCA-22JH83 | Botanica (Stage 3) | Build Commenced | Build Preparation |
AYCA-22JVJT | Botanica (Stage 4) | Build Commenced | Build Preparation |
AYCA-22NWGZ | Woodlands Edge (Stage 5) | Build Commenced | Build Preparation |
AYCA-22WTO1 | Heron Park (Stage 10D) | Build Commenced | Build Preparation |
AYCA-22X7Z0 | Southlakes Estate (Stage CC15A) | Build Commenced | Build Preparation |
AYCA-233ZWE | Morningside (Stage 1) | Build Commenced | Build Preparation |
AYCA-235DFV | Rivergreen Villas (Stage 12) | Build Commenced | Build Preparation |
AYCA-238B80 | Merrifield Gardens (Stage 2) | Build Commenced | Build Preparation |
AYCA-23FLGP | Thornton West Estate (Stage 2) | Build Commenced | Build Preparation |
AYCA-23LD4F | Clarinda Estate (Stage 5) | Build Commenced | Build Preparation |
AYCA-23YXCN | 90 Emu Road, Caboolture (Stage 4) | Build Commenced | Build Preparation |
AYCA-2406S0 | Evans Park Cranbourne West (Stage 1) | Build Commenced | Build Preparation |
AYCA-2436TV | Sovereign Hills (Stage College Rise Release 2) | Build Commenced | Build Preparation |
AYCA-244NZQ | Sunset Ridge Estate (Stage 1) | Build Commenced | Build Preparation |
AYCA-24B7B4 | Central Villas (Stage 1) | Build Commenced | Build Preparation |
AYCA-24KBWS | Cardinia Views Estate (Stage 4) | Build Commenced | Build Preparation |
AYCA-24LCO2 | Watermark (Stage 1) | Build Commenced | Build Preparation |
AYCA-24ZTI7 | East Village (Stage 1) | Build Commenced | Build Preparation |
AYCA-258U47 | Mill Street, Meadows Land Dev (Stage 4) | Build Commenced | Build Preparation |
AYCA-25ER6M | 84 Dixon Drive (Stage 1A) | Build Commenced | Build Preparation |
AYCA-25ER7W | 84 Dixon Drive (Stage 1B) | Build Commenced | Build Preparation |
AYCA-25GINX | Vale (Stage 38) | Build Commenced | Build Preparation |
AYCA-25MIYL | Retallick subdivision (Stage 1) | Build Commenced | Build Preparation |
AYCA-25ZGVX | Muller Street, Redland Bay (Stage 1) | Build Commenced | Build Preparation |
AYCA-26IBT2 | 829 Richmond Rd (Stage 5) | Build Commenced | Build Preparation |
AYCA-29ADHR | Yorkdale Estate (Stage 15) | Build Commenced | Build Preparation |
AYCA-29RAWP | Skybrook Stage 3 (Stage 3) | Build Commenced | Build Preparation |
AYCA-29TXEO | Calleya (Stage 28) | Build Commenced | Build Preparation |
AYCA-29TXG7 | Calleya (Stage 30) | Build Commenced | Build Preparation |
AYCA-2B3RRS | Haywards Bay (Stage 8) | Build Commenced | Build Preparation |
AYCA-2B486P | Alma Villas (Stage 1) | Build Commenced | Build Preparation |
AYCA-2BL9TE | Osprey Waters, Erskine (Stage 4) | Build Commenced | Build Preparation |
AYCA-2D3XYC | Kearneys Dr (Stage 1) | Build Commenced | Build Preparation |
AYCA-2D6ZKP | Narangba Heights (Stage 4) | Build Commenced | Build Preparation |
AYCA-2DDJ62 | Lakeview Apartments (Stage 1) | Build Commenced | Build Preparation |
AYCA-2E7WSZ | The Meadows (Stage Karingal – 2A) | Build Commenced | Build Preparation |
AYCA-2FTRKL | Wybenia Estate (Stage 1) | Build Commenced | Build Preparation |
AYCA-2H1RX2 | 84 Dixon Drive (Stage 3B) | Build Commenced | Build Preparation |
AYCA-2H1Y3Z | 84 Dixon Drive (Stage 3A) | Build Commenced | Build Preparation |
AYCA-2H1Y7A | 84 Dixon Drive (Stage 3C) | Build Commenced | Build Preparation |
AYCA-2H2B6Z | 91-93 Nicholson Street (Stage 1) | Build Commenced | Build Preparation |
AYCA-2HCZ8F | 19 Cranley Street Villas (Stage 1) | Build Commenced | Build Preparation |
AYCA-2HDGMB | Govetts Street (Stage 1) | Build Commenced | Build Preparation |
AYCA-2HIC0F | Jimboomba Woods (Stage 22) | Build Commenced | Build Preparation |
AYCA-2I5J5C | 50 Cameron Street, Doonside (Stage 1) | Build Commenced | Build Preparation |
AYCA-2IGLV4 | 170 Riverstone Road (Stage 2A) | Build Commenced | Build Preparation |
AYCA-2IR0B6 | Pimpama Rivers Estate (Stage 14B) | Build Commenced | Build Preparation |
AYCA-2IS2U6 | Maragon Early Childhood Centre, Wellard (Stage 1) | Build Commenced | Build Preparation |
AYCA-2J5UE5 | Banyo Shopping Centre (Stage 1) | Build Commenced | N/A (new in April 2016) |
AYCA-2JD6OW | Amy Street Community Title Development (Stage 1) | Build Commenced | Build Preparation |
AYCA-2LXQ9T | Canterbury Estate (Stage 3) | Build Commenced | Build Preparation |
AYCA-2MOAQ4 | Parkside Coomera (Stage 5) | Build Commenced | N/A (new in April 2016) |
AYCA-2MPOU8 | HC - Revitalise Circuit Units (Stage 1) | Build Commenced | Build Preparation |
AYCA-2MYYMQ | Block3 Section 15 Wright (Stage 1) | Build Commenced | N/A (new in April 2016) |
AYCA-2O1ZN9 | 9 - 11 Hancock Street Apartments (Stage 1) | Build Commenced | Build Preparation |
AYCA-2OOES0 | Paech Road Residential Subdivision (Stage 5) | Build Commenced | Build Preparation |
AYCA-2PMDBY | Pimpama Rivers Estate (Stage 14C) | Build Commenced | Build Preparation |
AYCA-2POVS4 | Walka Grange (Stage 5) | Build Commenced | Build Preparation |
AYCA-2S7FG3 | Supreme Loop (Stage 1) | Build Commenced | Build Preparation |
AYCA-2SDP93 | Arthur St (Stage 2) | Build Commenced | Build Preparation |
AYCA-2UEUQA | Jade Townhouses (Stage 1) | Build Commenced | Build Preparation |
AYCA-323I48 | 88 (Stage 1&2 - SP2) | Build Commenced | N/A (new in April 2016) |
AYCA-FP82I | Beaudesert Rd, Algester (Stage 1) | Build Commenced | Build Preparation |
AYCA-HZYI5 | NYLANDER ROAD, BUNYIP (Stage 1) | Build Commenced | Build Preparation |
AYCA-NS3YV | The Catalina (Stage WAPC 583-12) | Build Commenced | Build Preparation |
AYCA-T73ZY | Discovery Point (Stage Bldngs 8,9&10) | Build Commenced | Build Preparation |
AYCA-TTYRP | GOOLWA NORTH (Stage ONE) | Build Commenced | Build Preparation |
AYCA-XC501 | Harvest Views Estate (Stage 2A) | Build Commenced | Build Preparation |
AYCA-XGZCF | French Street Werrington (Stage 1&2) | Build Commenced | Build Preparation |
AYCA-ZOXTS | Sienna Wood (Stage Riverbend Stage 1) | Build Commenced | Build Preparation |
AYCA-ZVLVO | Oaktree Rise Estate (Stage 7) | Build Commenced | Build Preparation |
Now active in these new developments
Rollout Region | Locality | April 2016 Status | March 2016 Status |
---|---|---|---|
AYCA-127KEM | Melbourne (Stage SP1) | Active | Build Commenced |
AYCA-13RQQ0 | Gwandalan Residential Subdivision (Stage 2) | Active | Build Commenced |
AYCA-13ZML3 | 15-18 Charles Street Canterbury (Stage 1) | Active | Build Commenced |
AYCA-14OCGC | Rockbank North (Woodlea) (Stage 1) | Active | Build Commenced |
AYCA-16O5P3 | The Meadows (Stage 2) | Active | Build Commenced |
AYCA-17OKR5 | Green Orchid Gardens (Stage 3) | Active | Build Commenced |
AYCA-17R3RO | Caversham Development Project (Stage 1B) | Active | Build Commenced |
AYCA-18CEYN | Elmstead Estate (Stage E6) | Active | Build Commenced |
AYCA-18LJTP | St Leonards Estate (Stage 1O) | Active | Build Commenced |
AYCA-1964BJ | Chenel Private Estate (Stage Lot 19) | Active | Build Commenced |
AYCA-1964FR | Chenel Private Estate (Stage Lot 21) | Active | Build Commenced |
AYCA-197PI4 | Kilora - 335 Grices Road (Stage 2) | Active | Build Commenced |
AYCA-1AB7AX | Coburg Hill Development (Stage 6) | Active | Build Commenced |
AYCA-1B3HE6 | Twin Waters Estate (Stage 5) | Active | Build Commenced |
AYCA-1BQLQ5 | Newstead Towers (Stage SP1) | Active | Build Preparation |
AYCA-1C3D2T | Tuart Ridge (Stage Retail & Residential) | Active | Build Commenced |
AYCA-1CDO3M | Norfolk Estates Pty Ltd (Stage 5) | Active | Build Commenced |
AYCA-1CFR3S | Elmstead Estate (Stage E5) | Active | Build Commenced |
AYCA-1COO1O | Bellefields (Stage 3) | Active | Build Commenced |
AYCA-1CR6BS | Lot 72 Schofields Farm Road (Stage 1) | Active | Build Commenced |
AYCA-1CR6ZF | North Rocks (Stage 2) | Active | Build Commenced |
AYCA-1D0M7A | Trinity Point (Stage 5) | Active | Build Commenced |
AYCA-1D655Q | Elmstead Estate (Stage E4) | Active | Build Commenced |
AYCA-1DVC4H | Cambridge Rise Estate (Stage 1) | Active | Build Commenced |
AYCA-1E25PF | Grandvue Estate (Stage 9B) | Active | Build Commenced |
AYCA-1EBGUR | Vincent Road, Sinagra (Stage 5A) | Active | Build Preparation |
AYCA-1EBZZT | Bullsbrook Landing (Stage 5) | Active | Build Commenced |
AYCA-1EPYR6 | 135 Southern Cross Ave Middleton Grange (Stage 1) | Active | Build Commenced |
AYCA-1FPCFZ | Cassia Glades (Stage 1A) | Active | Build Commenced |
AYCA-1FYTJZ | Solitary Island View Estate (Stage 1) | Active | Build Preparation |
AYCA-1G6PCL | Vasse Newtown (Stage VC1A) | Active | Build Commenced |
AYCA-1G8QXW | Whitby (Stage 1B) | Active | Build Commenced |
AYCA-1GCO65 | Whitby (Stage 1A) | Active | Build Commenced |
AYCA-1GEQN4 | Grandvue Estate (Stage 9C) | Active | Build Commenced |
AYCA-1GQW3W | Scarborough Hotel Landsborough Ave (Stage 1) | Active | Build Commenced |
AYCA-1HO8VJ | Lomond Views Estate (Stage 9) | Active | Build Commenced |
AYCA-1HPVXP | Rockbank North (Woodlea) (Stage 2) | Active | N/A (new in April 2016) |
AYCA-1I58T9 | Vale (Stage 11B) | Active | Build Commenced |
AYCA-1I5D3S | Baldivis East (Stage 3) | Active | Build Commenced |
AYCA-1I9G4T | Vale (Stage 11C) | Active | Build Commenced |
AYCA-1ILZDT | Springtime 2 (Stage 2A) | Active | Build Commenced |
AYCA-1JG1CU | Spring Mountain (Stage 11A) | Active | Build Commenced |
AYCA-1JLPWP | Casey Marketplace (Stage SP1) | Active | Build Commenced |
AYCA-1JRP8M | The Pasco (Stage SP1) | Active | Build Commenced |
AYCA-1JYXHE | Lot 18, Sixty Eight Road (Stage 3) | Active | Build Commenced |
AYCA-1K2IHH | Marden Connect (Stage 5, 7,9,10,11) | Active | Build Commenced |
AYCA-1K93Q3 | Googong Township (Stage NH1A Stages 5A & 5B) | Active | Build Commenced |
AYCA-1KGETF | South at Seaford Meadows (Stage 7C3) | Active | Build Commenced |
AYCA-1KJ33I | Radius Apartments (Stage 1) | Active | Build Commenced |
AYCA-1KKL4H | The Avenue (Stage 2) | Active | Build Commenced |
AYCA-1KPYI3 | Heron Park (Stage 23) | Active | Build Commenced |
AYCA-1L0UDJ | CRYSTAL GARDENS (Stage 1) | Active | Build Commenced |
AYCA-1LPKW2 | Goulburn Road, Baldivis (Stage 1) | Active | Build Commenced |
AYCA-1MI4GK | Moncrieff Residential Estate (Stage 2A (East)) | Active | Build Commenced |
AYCA-1N49WA | 61-67 Caboolture River Rd (Stage 1) | Active | Build Commenced |
AYCA-1N588A | Arthur St (Stage 1) | Active | Build Commenced |
AYCA-1NBE4E | Harcrest (Stage 5B & 5M & 5W) | Active | Build Commenced |
AYCA-1NEOEU | Burch Way Units (Stage 1 (Lot 151)) | Active | Build Commenced |
AYCA-1NXR80 | Orana (Stage 1) | Active | Build Commenced |
AYCA-1NZGD6 | 61-67 Caboolture River Rd (Stage 2) | Active | Build Commenced |
AYCA-1O095S | Lot 9500 Briggs Road, Byford WA (Stage 1) | Active | Build Commenced |
AYCA-1O7QXO | Riverstone Crossing (Stage 10A) | Active | Build Commenced |
AYCA-1OUM49 | Gailes (Stage 1) | Active | Build Commenced |
AYCA-1OV933 | 1OAK (Stage SP-1) | Active | Build Commenced |
AYCA-1P7OGA | Parklakes Estate (Stage 1C) | Active | Build Commenced |
AYCA-1P80S4 | Providence - SUCE (Stage 5) | Active | Build Commenced |
AYCA-1P85PR | Providence - SUCE (Stage 6) | Active | Build Commenced |
AYCA-1P8IES | Highland Reserve (Stage 20B & 20D) | Active | Build Commenced |
AYCA-1P8IO5 | Highland Reserve (Stage 22A) | Active | Build Commenced |
AYCA-1P9KI6 | Lot 374 Alcock Street, Maddington (Stage 1) | Active | Build Commenced |
AYCA-1PBR8C | Gardene (Stage 1) | Active | Build Commenced |
AYCA-1PBRTE | Marden Connect (Stage 13,14) | Active | Build Commenced |
AYCA-1PL6EG | Royal Shores Ermington West (Stage Lot 305) | Active | Build Preparation |
AYCA-1POMKR | GVH-086 2 Burch Way Units (Stage 1 (Lot 152)) | Active | Build Commenced |
AYCA-1PQPDG | Brighton Lakes (NBGC) (Stage 2) | Active | Build Commenced |
AYCA-1PQT2Z | Keswick on the Park (Stage 1) | Active | Build Commenced |
AYCA-1QGN7U | Tallowood Ridge (Stage 3B) | Active | Build Commenced |
AYCA-1QKKS8 | Brierley Hill (Stage 8) | Active | Build Commenced |
AYCA-1QV0PB | Allura Estate (Stage 38) | Active | Build Commenced |
AYCA-1QZMUI | Fairways (Stage 5) | Active | Build Commenced |
AYCA-1RBY4L | The Shores (Stage 1A & 1B) | Active | Build Commenced |
AYCA-1RC93R | Subdivision of Lot 3333, Katherine East (Stage 1) | Active | Build Commenced |
AYCA-1RE9T1 | Allura Estate (Stage 42) | Active | Build Commenced |
AYCA-1RITCW | Vale (Stage 24) | Active | Build Commenced |
AYCA-1S74X7 | Macquarie Park (Stage 1 (Building 2)) | Active | Build Commenced |
AYCA-1SGV91 | Lomond Views Estate (Stage 10 & 11) | Active | Build Commenced |
AYCA-1TQHUC | Kimberley Downs Estate (Stage 10) | Active | Build Commenced |
AYCA-1TUND3 | Tangadee Rd Units (Stage 1) | Active | Build Commenced |
AYCA-1TW5MH | PARKINSON TOWNHOUSE DEVELOPMENT (Stage 1) | Active | Build Commenced |
AYCA-1U63ZY | Appin Rise (Stage 1) | Active | Build Commenced |
AYCA-1UKIZC | KORORA BEACH DEV. (Stage 1) | Active | Build Commenced |
AYCA-1UQ4AY | 98 Dixon Drive Pimpama (Stage 4) | Active | Build Commenced |
AYCA-1UQ4KC | 98 Dixon Drive Pimpama (Stage 5) | Active | Build Commenced |
AYCA-1UQ4TD | 98 Dixon Drive Pimpama (Stage 6) | Active | Build Commenced |
AYCA-1UW26O | Teviot Downs Estate (Stage 33) | Active | Build Commenced |
AYCA-1UZ4ME | Southlakes Estate (Stage CC14) | Active | Build Commenced |
AYCA-1VIZGD | Parks Edge @ Casey Fields (Stage 6) | Active | Build Commenced |
AYCA-1VJE2E | Sandstone Lakes (Stage 10) | Active | Build Commenced |
AYCA-1VK3LB | The Vale (The Ridge) (Stage 8) | Active | Build Commenced |
AYCA-1VK7AQ | The Springs - Tribeca (Stage South) | Active | Build Commenced |
AYCA-1VOIA7 | The Vale (The Ridge) (Stage 9B) | Active | Build Commenced |
AYCA-1VR9PK | Golf Links (Stage 4) | Active | Build Commenced |
AYCA-1VRE2J | 66 Ellam Drive, Seven Hills (Stage 1) | Active | Build Preparation |
AYCA-1VRUM9 | South East Thornlands (Stage 2) | Active | Build Commenced |
AYCA-1WA56B | Manor Lakes (Stage 133) | Active | Build Commenced |
AYCA-1WDY29 | Oatley Close (Stage 1) | Active | Build Commenced |
AYCA-1WSQ6T | Stone Ridge (Stage 2) | Active | Build Commenced |
AYCA-1WSQGH | Stone Ridge (Stage 3) | Active | Build Commenced |
AYCA-1WYCMR | Pimpama Village (Stage 2) | Active | Build Commenced |
AYCA-1XAQKR | Greenway - 799 Richmond Rd (Stage 3) | Active | Build Commenced |
AYCA-1XE34N | Stone Ridge (Stage 5 & 6) | Active | Build Commenced |
AYCA-1YL6RW | Freeling Estate 2 (Stage 7) | Active | Build Commenced |
AYCA-1Z6JYF | North Shore (Stage 212) | Active | Build Commenced |
AYCA-1Z8XJY | Provence (Stage 16A1) | Active | Build Commenced |
AYCA-1ZBCCM | Gateway of Findon (Stage 48) | Active | Build Commenced |
AYCA-1ZSS2T | SPRING FARM (Stage 5A) | Active | Build Commenced |
AYCA-1ZSW7V | SPRING FARM (Stage 5B) | Active | Build Commenced |
AYCA-201EPH | Parklakes Estate (Stage 1B) | Active | Build Commenced |
AYCA-217SPF | The Corso, North Lakes (Stage 1-Mar) | Active | Build Commenced |
AYCA-217WBT | Oceanside Car Park (Stage 1) | Active | Build Commenced |
AYCA-21N2GN | LATITUDE ALDINGA BEACH (Stage 3) | Active | Build Commenced |
AYCA-21Q672 | 34 Sunbury Rd, Victoria Park (Stage 1) | Active | Build Commenced |
AYCA-21RDMU | 4 couche (Stage 1) | Active | Build Preparation |
AYCA-22IZ93 | Paramount Apartments (Stage 1) | Active | Build Commenced |
AYCA-235DDU | Rivergreen Villas (Stage 10) | Active | Build Commenced |
AYCA-23L42G | Carrington Park (Stage 5) | Active | Build Commenced |
AYCA-23LF13 | Pavillions Stage 10 - 19 (Stage 10) | Active | Build Commenced |
AYCA-23LF3Z | Pavillions Stage 10 - 19 (Stage 12) | Active | Build Commenced |
AYCA-23N5LC | 298 melton rd (Stage 1) | Active | Build Commenced |
AYCA-23PCOD | 2a Clydesdale Street (Stage 1) | Active | Build Commenced |
AYCA-24XP1K | Brunslea Park Estate (Stage 13) | Active | Build Commenced |
AYCA-25A35A | Dempster Terraces (Stage 1) | Active | Build Commenced |
AYCA-26RHH1 | Brightwater Estate (Stage 35A, 32A & 28A) | Active | Build Preparation |
AYCA-297PRX | Kallangur Townhouses (Stage 1) | Active | Build Commenced |
AYCA-2AIHXY | 212 Kooyong RD, Rivervale (Stage 1) | Active | Build Commenced |
AYCA-2ARFKO | Kokoda Street (Stage 1) | Active | Build Commenced |
AYCA-2B4AHG | 51 Menser Street (Stage 1) | Active | Build Commenced |
AYCA-2BCM0H | Timbertop (Stage L) | Active | Build Preparation |
AYCA-2BJDX2 | Magnolia Estate (Stage 2) | Active | Build Commenced |
AYCA-2C0Y5T | Aspire (Stage 1) | Active | Build Commenced |
AYCA-2E375X | Eliza Ponds Estate - Ocean Meadows 1 (Stage 1) | Active | Build Preparation |
AYCA-2ECJGL | Light House Estate (Stage 1) | Active | Build Commenced |
AYCA-2GTFOK | 57 Chantelle Parade, Tarneit (Stage 1) | Active | Build Preparation |
AYCA-2HRBMP | 175-179 Jamison Rd (Stage 1) | Active | Build Preparation |
AYCA-2OW6T5 | Brightwater Estate (Stage 28) | Active | Build Commenced |
AYCA-2P2OA6 | Newhaven (Stage Pad Sites) | Active | Build Commenced |
AYCA-E4ETU | Little Bay Cove (Stage 1 & 2 (West)) | Active | Build Commenced |
AYCA-MJP2H | TRIESTE (Stage 1) | Active | Build Commenced |
AYCA-MOSXD | 29 Hunter Street Parramatta (Stage SP1) | Active | Build Commenced |
AYCA-P0IAI | TOGA Hurstville (Stage 1) | Active | Build Commenced |
AYCA-SG6C8 | Alkira Estate (Stage 3) | Active | Build Commenced |
AYCA-WA49T | THE RISE (Stage 4) | Active | Build Commenced |
AYCA-X6KZ8 | Vicland Development (Stage V2 Boxhill) | Active | Build Commenced |
AYCA-Z3K5O | Johns Road Wadalba (Stage 1, 2 & 3) | Active | Build Commenced |
AYCA-ZIFL1 | Gwandalan Residential Subdivision (Stage 1) | Active | Build Commenced |